FY 2017 CPA Projects & Town Meeting Articles

Applications for Fiscal Year 2017 Community Preservation Act Project Funding May 2016 Town Meeting



Recreation:


1) $1,130,000  ($98,875 est. FY17 debt service) for Creation of Recreational Land (Case Campus Master Plan - Construction) 
Further Information:
Application
CPC Public Hearing presentation
CPC April 4th meeting presentation
Handouts at CPC Public Hearing - Construction Cost Estimates, Summary Estimate Level, Project Manager Email 
Summary Bid Information

2) $30,000 for Creation of Recreational Land (Merriam Street Sidewalk Final Design)
Further Information
Application
CPC Public Hearing presentation

3) $250,000 for Creation of Recreational Land (Brown/Winter Street Sidewalk Construction)
Further Information:  
Application
CPC Public Hearing presentation
Handout at CPC Public Hearing - Winter Gardens Petition

Open Space


4) $10,000 for Preservation of Open Space (Charles River Invasive Species Removal)
Further Information
Application 

Historic Resources


5) $364,000 for Preservation of Historic Resources (Old Library – Weston Art & Innovation Center Proposal)
Further Information:  
Application
CPC Public Hearing presentation
Handouts at CPC Public Hearing

Community Housing


6) $16,163 for Support for Community Housing (Staff Support & Regional Housing Office)
Further Information:  
Application


TOTAL FY17 CPA FUNDS REQUESTED:  $769,038