Sudbury Road/Ripley Lane Road Construction

rdconst.jpg

Weston's DPW will be installing the binder course paving on Ripley Road on Friday, July 28th. The work is anticipated to take only a few hours.


Starting on Monday, July 31st, Weston's DPW will be installing the binder course paving on Sudbury Road. Since this is a longer stretch of road it is anticipated to take two days to complete.


Detours will be in place to direct traffic around the project area.


Thank you for your patience and cooperation during construction.