751-761 Boston Post Road

180 rental units on 12 acres within a total of 62-acres

Mill Creek Residential has filed a Comprehensive Permit application with the Zoning Board of Appeals for Modera Weston. 

The comprehensive permit public hearing is anticipated to be closed on September 16, 2020. Once the hearing closes, the ZBA must issue a decision within 40-days of the vote to close the hearings.

Find the information presented during the public hearing process, which was opened on June 10, 2019 with an agreed-upon extension due to the coronavirus health emergency. Follow the public hearing process by subscribing to receive meeting and/or agenda notifications at weston.org/stayinformed

See the affordable housing web page under Town Projects to review the Project Eligibility Letter and past information session materials.

Final Hearing: September 16, 2020

Modera Weston

modera weston broader view

Continued Hearing - August 11, 2020

Continued Hearing - July 21, 2020

Continued Hearing: June 16, 2020

Continued Hearing: May 12, 2020

Continued Hearing: March 12, 2020

Continued Hearing: January 27, 2020

Continued Hearing - October 23, 2019

Continued Hearing - September 23, 2019

Continued Hearing - August 12, 2019

Continued Hearing - July 8, 2019

Comprehensive Permit Application Documents