751-761 Boston Post Road
180 rental units on 12 acres within a total of 62-acres
The Zoning Board of Appeals approved the comprehensive permit for Modera Weston on November 24, 2020. The final decision is located below, along with the plans and materials presented during the hearing process.
The decision is under appeal (2021).
Request for a Minor Modification
On July 28, 2022, the Zoning Board of Appeals met and voted that a reduction in the number of dwelling units was an insubstantial modification to the Decision.
Revised Final Comprehensive Permit under M.G.L. 40
Appeal Discussions 2021
Final Decision - Nov. 24, 2020
Continued Hearing - July 21, 2020
Continued Hearing: May 12, 2020
- Agreement to Continue Public Hearing (PDF)
- Arcadis: Proposed Conditions for Permitting - March 16 (PDF)
- Final Road Safety Audit - Wayland - MassDOT Check - April 29 (PDF)
- Final Road Safety Audit - Weston - MassDOT Check - April 29 (PDF)
- Mill Creek Response to SMP Requirements March 19 (PDF)
- Peer Civil Engineer Memo May 11 (PDF)
Continued Hearing: March 12, 2020
Continued Hearing: March 4, 2020
- Arcadis Environmental Conditions of Permit Memo - Feb. 27 (PDF)
- Cambridge Water Department Comments on the Wetlands Permit (PDF)
- Cambridge Water Dept. Comments Re: Soil Remediation - March 3 (PDF)
- Conservation Commission Order of Conditions for Modera Permitting (PDF)
- DEP Appeal of Conservation Commission Orders of Conditions - Feb. 26 (PDF)
- Draft Road Safety Audit: Rt. 20 at Highland St and Love Ln. - Feb. 18 (PDF)
- GZA Proposed Soil Management and Remediation Plan - Feb. 20 (PDF)
- Mill Creek Residential Response to Arcadis - March 3 (PDF)
- Modera Weston Invasive Management Plan - Feb. (PDF)
- Modera Weston Site Planting - Feb. (PDF)
- Modera Weston Waivers List - March 3 (PDF)
- Operations & Maintenance Stormwater Plan Revisions from Cambridge Water Dept. (PDF)
Continued Hearing: January 27, 2020
- Modera Weston Plan Set - Jan. 23, 2020 (PDF)
- Site Plan: Material Layout (PDF)
- Stormwater Mgt. System: Operation & Maintenance, LT Pollution Prevention Plans (PDF)
- Peer Review no. 5: Plan Set and Stormwater Mgt. System (PDF)
- Additional Sampling Results Jan. 22, 2020
- Arcadis Peer Review Memo: Additional Sampling Jan. 27 (PDF)
Continued Hearing: Dec. 9 & 10, 2019
- Arcadis Memo - Environmental Site Assessment Review (PDF)
- Attachment B - Landscape Architectural Plans (PDF)
- Attachment C - Architectural Drawings (PDF)
- Construction Management Plan Dec. 4 (PDF)
- GZA GeoEnvironmental Response to Arcadis - Additional Sampling Dec. 8 (PDF)
- Historical Commission Memo to ZBA (PDF)
- Layout and Materials Plan (PDF)
- MetroWest Engineering Peer Review no. 4 - Dec. 3 (PDF)
- Modera Weston - Presentation to ZBA - December 10th (PDF)
- Modera Weston - Presentation to ZBA - December 9th (PDF)
- Modera Weston Holistic Update to ZBA Dec. 3 (PDF)
- Proposed Sampling Plan presented Dec. 10 (PDF)
- Response to Transportation Peer Review Dec. 3 (PDF)
- Revised Permit Plans: Nov. 22, 2019 (PDF)
- Revised Stormwater Report: Nov. 22, 2019 (PDF)
- Town Rights in Elliston Road Memo - Nov. 19 (PDF)
Continued Hearing - October 23, 2019
Continued Hearing - September 23, 2019
Continued Hearing - July 8, 2019
- Civil Engineering Permit Plans (PDF)
- Concept Site Landscape Plan (PDF)
- Existing Conditions Survey (PDF)
- Traffic Impact Study: Peer Review - June 28, 2019 (PDF)
- July 1, 2019 Memo: Traffic Volume Comparison (PDF)
- Affordable Housing Trust Letter to ZBA - June 18, 2019 (PDF)
- Historical Commission Memo to ZBA July 6, 2019 (PDF)
- Planning Board Letter to ZBA - June 19, 2019 (PDF)
- Modera Weston Response to Planning Board Letter - July 1, 2019 (PDF)
- Preliminary Geotechnical and Environmental Study (PDF)
- Preliminary Floor Plans Indicating Proposed Revisions (PDF)
- Revised Building Design Exhibits (PDF)
Comprehensive Permit Application Documents
Filed May 20, 2019, Hearing opened June 10
- 00. Comprehensive Permit Application Cover Letter (PDF)
- 00.1. Signed Project Eligibility Letter from MassHousing (PDF)
- 01. ZBA Comprehensive Permit Application (PDF)
- 03. Report of Existing Conditions (PDF)
- 06. Requested Waivers (PDF)
- 08. Town GIS Map (PDF)
- 09. Traffic Impact Assessment (PDF)
- 10. Comp Permit Drawings (PDF)