Posted on: June 11, 2020

Roadway Construction on Ash and Church Streets

cones200

Weston Department of Public Works will begin roadway reconstruction on Church Street and Ash Street the week of June 15th. Work is anticipated to take three to five weeks and is weather dependent.

Church Street

  • Work is tentatively scheduled to begin on Monday the 15th
  • Work limit is from Conant Road to house no. 214 (close to North Ave.)
  • First, the road surface will be milled
  • Next, utility castings (catch basins, manholes, etc.) will be adjusted
  • Next, the pavement will be installed
  • Final, the pavement markings will be reinstalled
  • Residents will have access to their homes
  • Emergency vehicles will have access
  • Expect delays

Ash Street

  • Work is tentatively scheduled to begin on Wednesday the 17th
  • Work limit is from South Avenue to the reservoir, then from house no. 211 to the end
  • First, the road surface will be milled
  • Next, utility castings (catch basins, manholes, etc.) will be adjusted
  • Next, the pavement will be installed
  • Final, the pavement markings will be reinstalled
  • Residents will have access to their homes
  • Emergency vehicles will have access
  • Expect delays

Anticipated 2020 Roadway Season

Some of the streets listed below are dependent upon the completion of water, drainage, and gas work, as well as funding

  • Arrowhead Road - Bakers Hill Road to Bakers Hill Road - anticipate starting June
  • October Lane - Bakers Hill Road to Conant Road - anticipate starting June
  • Kings Grant Road - Spruce Hill Road to cul de sac
  • Spruce Hill Road - Kings Grant Road to cul de sac
  • Bay State Road - Spruce Hill Road to end
  • Indian Hill Road - Kings Grant Road to end
  • Webster Road - Church Street to Church Street
  • Buckskin Road - Route 20 to town line
  • Warren Avenue - Boston Post Road to Gun Club Lane
  • Merriam Street - Silver Hill Road to Sunset Road (expect road closure and detour)
  • Newton Street - #150 to South Avenue
  • Spring Lane - Conant Road to end of roadway

Please note:

  • To follow the roadway program above, subscribe to receive weekly work updates from Weston’s DPW
  • Some roadway construction is not a part of the Town’s capital improvement projects, such as National Grid gas main replacements. Those roadways are also listed in the DPW work updates
  • To find the five-year schedule of road paving, please visit Weston.org/DPW to find the Capital Improvement Plans web page where the Five-year Roadway Improvement Program and Map are listed

Moratorium on Road Cutting after Paving 

Once paving is completed on any town-owned roadway in Weston, a five-year moratorium on pavement cutting is placed on that road. This is done to protect the investment made by taxpayers. Please refer to the Five-year Roadway Improvement Program and Map if you are planning any home reconstruction where utility lines will be impacted.